1. After what service life of winding rope in years, it shall not be re-used for winding purposes?

2 / 40

2. The space between detaching hook and the detaching-bell or plate at its normal position at the top of the shaft, shall not be less than----------meters where a geared engine is used.

3 / 40

3. The provisions regarding aggress in a shaft are not applicable in the case of

4 / 40

4. When white metal is poured into the socket its temperature shall not exceed -----------degrees centigrade.

5 / 40

5. The depth-indicator shall be tested after every

6 / 40

6. Test of every automatic contrivance and every brake shall be made by competent person once in every-------------

7 / 40

7. All parts of suspension gear in regular use shall be renewed once in __ years or at shorter intervals.

8 / 40

8. The detaching hooks used in sinking shafts shall be cleaned and shear pin be replaced -----.

9 / 40

9. The melting point of white metal used in the capping of ropes melting point shall not exceed ---- degrees centigrade.

10 / 40

10. The winding equipment shall be checked by an engineer or other competent person once in at least -------- hours

11 / 40

11. The opening in a detaching bell or plate used shall be examined with calipers or gauges, once at least in ---------days

12 / 40

12. The space between detaching hook and the detaching-bell or plate at its normal position at the top of the shaft, shall not be less than---------meters where a direct acting engine is used.

13 / 40

13. The temperature to which the socket shall be heated before the white metal is poured into it is ----degrees centigrade.

14 / 40

14. When some heading is discontinued either temporarily or permanently a spot level is to be shown also at

15 / 40

15. Which of the following statements is correct

16 / 40

16. Copies of plans and sections are to be submitted to the Chief Inspector on or before.

17 / 40

17. Which of the following statement is correct

18 / 40

18. Proper platforms are also to be provided along with ladder/steps and hand rails, when the inclinations of the road increases more than 600. The spacing of the platform is.

19 / 40

19. The gap, both vertical and horizontal, between the protective roofing and the top of cage, when the cage is at the bottom of the shaft, shall not exceed

20 / 40

20. Where bent back wire cappel is used in the capping of ropes, the length of cappel shall not be less than ------times the diameter of the rope.

21 / 40

21. Except in the ’Koepe’ system of winding, every rope shall be recapped once at least in every -------

22 / 40

22. The two accesses like shafts, inclines or outlets shall not be less than --------meters distant from one another at any point.

23 / 40

23. The roads connecting the Shafts, inclines shall be.

24 / 40

24. Proper platforms are also to be provided along with ladder/steps and hand rails, when the inclinations of the road increases more than 600. The spacing of the platform is measured as under.

25 / 40

25. Once the cage reaches marking point at a permitted speed, the remaining distance should be wound at a speed of not more than.

26 / 40

26. The means of access and egress in a vertical shaft should be by mechanical means if the depth of such shaft exceeds

27 / 40

27. When gates are provided around a shaft the bottom of the gate shall not have clearance from the floor more than or rigid fences are to be proved in such a way that the gate or fence is not more ----------------above lift floor, and if it is fence it should not exceed ------------------.

28 / 40

28. Automatic contrivance and brake test shall be made by competent person by attempting to land the descending cage at excessive speed, once in.

29 / 40

29. Automatic contrivance system should be provided to prevent over speeding and over winding when the shaft depth exceeds.

30 / 40

30. Where any mine or seam or section is abandoned or discontinued over a period exceeding ----days, the owner of the mine should within -------days after the abandonment or within -------- days after the discontinuance of the workings, submit to the Chief Inspector two true copies of the up-to-date plan and sections of the workings.

31 / 40

31. When inhouse facilities are not available for testing a rope for its load strength, the test can be done through a recognised Government approved institution. The minimum length of rope length to be tested, attached to the cappel is__ mts.

32 / 40

32. After every installation or recapping of a rope the cage shall be fully loaded shall be moved up and down the working portion of the shaft and be examined. The number of times that the cage shall be moved before checking is___

33 / 40

33. On every side-tipping tub in use, safety-catches shall be provided to prevent accidental tipping. For the purpose of this Regulation, Two tubs are said to be in close succession when the distance between them at any time is less than ---------

34 / 40

34. The underground plans maintained shall show the boundaries of all adjacent mines as are situated within ----measured on any plane.

35 / 40

35. Every haulage rope shall be recapped once at least in every ---------months or shorter intervals as necessary.

36 / 40

36. when two such tubs are in tandem the gap between the inner most ends shall not be less than -------------------------

37 / 40

37. The levels that are marked are to be with reference to

38 / 40

38. When the sinking is in progress and when men are working below the height at which the cage can be kept is not more than_ meters.

39 / 40

39. If a change of ownership occurs within ___ days of abandonment or ___ days of discontinuance plans and sections shall be submitted forthwith.

40 / 40

40. Where means of ingress or egress is through ladder, its inclination shall not be more than__ Degrees from horizontal.